What a purchase order must contain

A purchase order, or PO, is the contract for one job. If it is not on the PO, the factory did not agree to it.

Field What it holds
PO number Your number, unique, and quoted on every message and box
Factory Who is making it
Product Style, fabric, cut and decoration method
Quantities A grid by size, with a total
Artwork The approved files, by name and version
Roster Names and numbers by size, if the product is personalized
Price Per piece, with any setup, and the currency
Ship-by date The day the goods leave the factory
Ship to Address and shipping method
Shipping terms Who pays freight and duties
Quality standard The approved sample or spec it must match, and how it will be inspected
Packing By player, by size or bulk, and how boxes are labeled
Payment terms Deposit, balance and when each is due

Two fields cause most disputes: the date and the quality standard. Write a ship-by date, not a delivery date, and name the sample or spec the goods will be checked against.

One purchase order, one factory

A customer's order often goes to more than one place. The jerseys go to a sublimation factory. The hoodies go to a screen printer. The caps go to an embroiderer.

Give each factory its own PO, linked to the same customer order. Each one can then be confirmed, tracked and late independently. An order with one line for three factories shows as "in production" until the day it is not.

The customer's ship date is then set by the slowest PO, and you can see which one that is.

Get a confirmation

A sent PO is not an accepted PO. Ask the factory to confirm three things in writing within a day: the quantities, the price and the ship-by date.

If the factory cannot meet the date, you want to hear it now, while you can move the job or reset the customer's expectations. A PO with no confirmation after a day gets a phone call.

Status by stage, on a schedule

Agree how the factory reports progress before the first order, and use stages, not adjectives. "Sewing, 60 of 140 done" is a status. "Going well" is not.

Two things make this work:

  • Fixed stages that both sides use. See production stages.
  • A fixed rhythm. The factory updates when a job changes stage, or at the same time every day.

Then you watch the exceptions. Any PO that has not moved in longer than that stage normally takes gets a question. The WIP report is where you see them.

Changes are written revisions

Customers add players. Sizes change. A sponsor logo arrives late. Every change after the PO is sent goes out as a numbered revision: PO 1042, revision 2, with what changed.

Ask the factory to confirm the revision and say whether the date or the price moves. A change agreed in a chat message is the one that will be missing from the box.

Set a cutoff. After cutting begins, changes become a new PO.

Receiving

Count every delivery against the PO the day it arrives, by size. For personalized orders, check names and numbers against the roster.

Record three things: what was short, what was wrong and what was damaged. Send the factory the list with photos the same day. Claims made a week later are harder to settle, and the customer's deadline has not moved.

Pay the balance after the count, or after a pre-shipment inspection for factories that ship direct to your customer.

Factories that ship direct to the customer

When the factory ships to the customer, you never see the goods. Three things replace your receiving check:

  1. Photos of the packed order and the packing list before it ships.
  2. The tracking number the day it leaves.
  3. A message to the customer asking them to count the delivery within two days.

Scorecards

Review each factory every quarter on the same numbers:

Measure How to calculate it
On-time rate POs shipped on or before the ship-by date, divided by POs shipped
Confirmation time Hours from PO sent to PO confirmed
Defect rate Pieces rejected, divided by pieces received
Shortage rate POs delivered short, divided by POs delivered
Average days late For late POs only

Share the numbers with the factory. Good factories want them. Then move volume toward the ones that perform, and say that this is how volume is decided.

Peak season

Every factory is full in the same weeks, before fall and spring seasons. Three habits help:

  • Tell your factories your expected volume a month or two ahead, even roughly.
  • Place POs as early as approvals allow. The line is first come, first served.
  • Keep a second qualified factory for each core product, and send it real work in quiet months so it knows your specs. See how to vet a manufacturer.

Mistakes

Ordering by chat. Messages get buried and nobody can find the final version.

A delivery date with no ship-by date.

No size grid. "140 jerseys, sizes to follow" is not an order.

Paying the balance before counting.

One factory for everything. The day it is late, every order is late.

Purchase orders in UniformsOS

In UniformsOS you send an order to a factory by choosing the factory and the units, and an order split across factories gets one purchase order for each. The factory signs in to its own portal, accepts the purchase order and reports the stage, and that moves the order on your side. A board shows open purchase orders by factory, by stage or by lateness. See Manufacturers and Vendors, Production WIP and UniformsOS for factories.

FAQ

What should an apparel purchase order include?
The product and decoration, quantities by size, approved artwork, price, ship-by date, shipping terms, the quality standard, packing instructions and payment terms.
What is the difference between a ship-by date and a delivery date?
The ship-by date is when the goods leave the factory. The delivery date is when they arrive. The factory controls the first one.
How do I split one customer order across factories?
Create a separate purchase order for each factory, all linked to the same customer order, and set the customer's date by the slowest one.
How often should a factory report status?
Whenever a job changes stage, or once a day at a fixed time.
When should I pay the factory's balance?
After you have counted the delivery against the purchase order, or after a pre-shipment inspection when the factory ships direct.

See UniformsOS on a live workspace

Thirty minutes on Google Meet with someone who has run a production floor on this system.